Closure to "Educating Civil Engineering Professionals of Tomorrow" by Symeon Christodoulou
(2005-04)
The discussion by Nirmal Kumar Acharya and Young-Dai Lee seems to focus on perceived limitations of FIAPP as applied to traditional civil engineering while pointing out that the original paper addresses primarily construction ...
A bid-unbalancing method for lowering a contractor's financial risk
(2008)
A method is presented for unbalancing bids and optimizing the allocation of overall project profits to individual activities by considering the financial parameters of a project (bid mark-up and projected cash flow), in ...
Construction imitating ants: Resource-unconstrained scheduling with artificial ants
(2009-05)
The paper presents a methodology to arrive at critical path calculations in construction networks by imitating the natural selection processes utilized by real-life ants in search of shortest paths to a food source, and ...